Town of Bristol issued the following announcement on January 27.
Dear Fellow Grafton County Communities,
In December, the Broadband Committee welcomed Enfield Town Manager Ed Morris. We are excited to have Ed on board!
Middle Mile (“Backbone”) Project Update
eX² Technology has completed detailed level final engineering designs for over half of the first 110 miles of the middle mile “backbone” included in Task Order No.001 of the contract with the County. As a reminder, Task Order No.001 consists of 13 links through the following communities/routes.... Read On